Activity rates from Quattrone Corporation's activity-based costing system are listed below. The company uses the activity rates to assign overhead costs to products:
|
| Activity Cost Pools | Activity Rate | |
| Processing customer orders | $101.81 | per customer order |
| Assembling products | $3.46 | per assembly hour |
| Setting up batches | $57.78 | per batch |
Last year, Product F76D involved 5 customer orders, 483 assembly hours, and 22 batches. How much overhead cost would be assigned to Product F76D using the activity-based costing system?
|
| $68,360.23 | |
| $1,271.16 | |
| $3,451.39 | |
| $1,598.08 |
The overhead cost charged to Product F76D is:
| Activity Cost Pools | Activity Rate | Activity | ABC Cost | |||
| Processing customer orders | $101.81 | per customer order | 5 | orders | $ 509.05 | |
| Assembling products | $3.46 | per assembly hour | 483 | hours | 1,671.18 | |
| Setting up batches | $57.78 | per batch | 22 | batches | 1,271.16 | |
$3,451.39
| ||||||