Karmazyn Hospital bases its budgets on patient-visits. The hospital's static budget for October appears below:
|
Budgeted number of patient-visits | 8,000 |
Budgeted variable costs: | |
Supplies (@ $8.10 per patient-visit) | $ 64,800 |
Laundry (@ $7.80 per patient-visit) |
62,400
|
Total variable cost |
127,200
|
Budgeted fixed costs: | |
Wages and salaries | 99,600 |
Occupancy costs |
107,600
|
Total fixed cost |
207,200
|
Total cost |
$334,400
|
The total variable cost at the activity level of 8,100 patient-visits per month should be:
$209,530 | |
→ | $128,790 |
$207,200 |
Budgeted number of patient-visits | 8,100 |
Budgeted variable costs: | |
Supplies (@ $8.10 per patient-visit) | $ 65,610 |
Laundry (@ $7.80 per patient-visit) |
63,180
|
Total variable cost |
$128,790
|